YILPORT Körfez Railway and Fast Discharge Pit Construction Project is Almost at the End

YILPORT Körfez railway and fast discharge pit construction project is almost at the end. This project will be a game-changer for YILPORT Körfez with numerous benefits including improved transportation, efficiency, and the expansion of Körfez’s hinterland.

Project status:
•The project is 95% complete. The work on the discharge pit has been completed, and the isolation part continues.
•The weighbridge foundation part has been completed and the infrastructure and installation works will be completed within 15 days.
• The project will be ready at the end of March.