YILPORT Gemlik RTG Block Construction Project Update

YILPORT Gemlik RTG Block Construction Project Update;

· The first phase of jet grout works is almost completed. The concrete work started on the beginning of RTG blocks

· The demolition of the warehouse was completed. Groundbreaking has begun.

· Half of the yard is planned to be handed over to operation by 2Q of 2022.

 